Whether you are building an application, running an event, or launching a new service; every project comes down to a set of tasks.
And to deliver on time you need to know two things:
Delivery timeline? Effort required?
This sounds simple. In reality, it is easy to get wrong especially if your team is small, new, or balancing multiple roles.
This guide will show you how to estimate task duration and effort using a practical, repeatable approach that works even if:
Let’s walk through a real-world example.
Let’s consider: You are leading a project to launch a product website in 4 weeks.
Your team includes:
Here is how you would estimate time and effort across tasks.
Forget tools for now, just write it down clearly.
Example deliverables:
Break them into tasks:
Tip: Don’t mix tasks like “design and develop homepage”, keep each step clear and separate.
This means: “If you had to do just this task, with no distractions; how long would it take you?”
Example:
Add them to a simple table:
| Task | Owner | Effort (hours) |
| Write homepage copy | Writer | 4 |
| Design homepage layout | Designer | 8 |
| Develop homepage | Developer | 12 |
Here is the trick: Effort ≠ duration.
If you assign the homepage build today, the developer might not start it until tomorrow or wait 2 days for copy and design.
You now estimate Duration (calendar time):
| Task | Effort (h) | Duration (days) | Notes |
| Write homepage copy | 4 | 1 | Can start right away |
| Design layout | 8 | 2 | Needs content draft first |
| Develop homepage | 12 | 3 | Depends on final design |
Tip: Ask “What do you need before you can begin this?” for every task.
For tasks that have approvals, back-and-forths, or are first-time processes; add 20–30% buffer.
Revised plan:
| Task | Effort (h) | Duration (days) | Buffered Duration |
| Write homepage copy | 4 | 1 | 1.2 days |
| Design layout | 8 | 2 | 2.5 days |
| Develop homepage | 12 | 3 | 3.5 days |
You can round these up when creating your Gantt chart or timeline.
Use a simple PM tool like:
Create columns for:
Example view in Google Sheets:
| Task | Owner | Effort | Duration | Start | End | Status |
| Homepage Copy | Writer | 4h | 1d | May 9 | May 10 | In Progress |
| Design Layout | Designer | 8h | 2d | May 10 | May 12 | Pending |
| Homepage Development | Developer | 12h | 3d | May 13 | May 16 | Not Started |
Your estimates will never be perfect. But they give you a reference point. Each week:
This lets you get better with every project.
Effort vs. Duration vs. Cost
Pro Tip: How to Estimate When You Have No Team Yet
If you are working solo or still hiring vendors:
You don’t need to be a professional estimator to build a solid plan. All you need is:
This approach scales across projects, whether you are building your first MVP or managing multiple client deliverables.